Project Regenerate!

On January 16th we embarked on the exciting phase of project construction works in Wesley's Worship Area.  Completion is programmed for the end of May.  Fundraising towards the project budget of £567,000 is going well; funds received and pledged now total just over £547,000. The Wesley Church Centre will remain open during the week and for Sunday services in the Hall throughout the construction period.  Midweek Worship services are being held in the Creche room.  'Music at Wesley' Tuesday Lunchtime Concerts are taking place in the Welsh Presbyterian Church across the road.

Project Regenerate! leaflet with background information

You can support our project through EASYFUNDRAISING.

Updates and progress: 


 Printable Version
<<  1 | 2
Week 5: Project Regenerate!
The main floor is now ready for trenches to be laid and construction of sleeper walls to begin to support joists. Boiler replacement will commence on Monday so temporary heating will be in place. Meanwhile, work will continue on the opening for the roof light and the light well underneath it.
Open 'Week 5: Project Regenerate!'

Week 4: Project Regenerate!
Armitage will be continuing with the excavation of the main floor and will begin digging out the pit for the rising stage. Construction of the new light well will proceed with new steels being installed. Scaffolding will be erected around the brick chimney ahead of boiler work commencing the following week.
Open 'Week 4: Project Regenerate!'

Week 3: Project Regenerate!
With the all scaffolding now in place, Armitage will start breaking open the ceiling and constructing the light well for the new roof light. Opening up of the roof above will also commence. Meanwhile, excavation of the floor will continue.
Open 'Week 3: Project Regenerate!'

Week 2: Project Regenerate!
Update 27th January 2017: Stripping out has gone well and the glazed pew has safely been moved to allow construction access through the display window by the pavement.
Open 'Week 2: Project Regenerate!'

Week 1: Project Regenerate!
This week, the main focus is to complete all protective work and create safe work access in the main loft.
Open 'Week 1: Project Regenerate!'

Project Regenerate begins!
An exciting week in Wesley's history as Project Regenerate begins.
Open 'Project Regenerate begins!'